What is management of change?

    Short answer

    Management of change (MOC) is the formal process an operation uses to identify, assess and control the risks introduced by a change, to equipment, process, materials, software, organisation or people, before the change is made and until it is embedded. It ensures the right people review the change, the hazards are addressed, affected documents and training are updated and the change is verified in use.

    Last updated · TeamAssurance

    Why management of change exists

    Many serious incidents trace back to a change that nobody assessed: a bypassed interlock, a new chemical, a reorganised shift, a software update, a temporary fix that became permanent. MOC makes the question "what could this change affect?" a required step rather than an afterthought.

    What counts as a change

    • Equipment: new, modified, relocated or temporarily altered plant, including bypasses.
    • Process: operating parameters, sequences, recipes, batch sizes.
    • Materials: new raw materials, chemicals, suppliers or packaging.
    • Systems: control software, data systems, alarms.
    • Organisation and people: roles, staffing levels, shift patterns, contractors.
    • Procedures: SOPs, standard work, permits.

    Replacement in kind, like for like with the same specification, is usually exempt; everything else goes through MOC.

    The MOC process

    1. Raise the change with a description, reason, scope and whether it is temporary or permanent.
    2. Assess the risks: hazards introduced or removed, effects on safety, quality, environment and operations, using a risk assessment or HAZOP as the change warrants.
    3. Define the controls and actions: engineering changes, procedure and training updates, communication, pre-start checks.
    4. Approve at the level matching the risk.
    5. Implement with the actions tracked to completion.
    6. Verify after start-up that the change performs as intended and the controls are in place, then close.
    7. Review temporary changes by their expiry date; extend formally or remove.

    Common failures

    • Temporary changes that are never closed.
    • Approvals treated as signatures rather than reviews.
    • Documents and training updated late or not at all.
    • No check that the change worked before it is declared complete.

    MOC and daily management

    Open changes, their actions and their verification dates belong on the relevant tier boards, so the Tier 2 meeting sees a temporary bypass approaching its expiry and the Tier 3 review sees the changes awaiting verification.

    How TeamAssurance helps

    In TeamAssurance a change can be managed as a tracked item with its risk assessment checklist, the actions it generates (owners, due dates), the updated standards it affects and a verification step before closure, all visible on the tier boards the site reviews. Overdue actions and expiring temporary changes are escalated through the tier meetings.

    Frequently asked questions

    What is the difference between management of change and change management?

    Management of change (MOC) is the risk-control process for a specific technical or organisational change, used in process safety and quality. Change management usually refers to the people side of organisational change: communication, adoption and resistance.

    Who approves a management of change?

    The level of approval matches the risk: a supervisor for a low-risk procedural change, the site leader or a technical authority for changes to safety-critical equipment or process. The MOC procedure defines the thresholds.

    How long can a temporary change stay in place?

    Only as long as the MOC approval states, typically days or weeks. At expiry it is either removed or formally reassessed and re-approved, so a temporary bypass cannot quietly become permanent.