Why changeover time matters
Long changeovers push operations toward large batches, which create inventory, hide defects and lengthen lead times. Shortening changeovers makes small batches economic, so production can follow demand. SMED is also one of the six big losses in OEE: set-up and adjustment.
The SMED steps
- Observe and record the current changeover. Video it; list every step with its time and whether the machine was stopped.
- Separate internal and external work. Internal steps need the machine stopped; external steps (fetching tools, preparing the next die, paperwork) can happen while it runs.
- Move external work out of the stop. Prepare everything before the machine stops. This alone often halves the changeover.
- Convert internal work to external. Pre-heat, pre-set, use standardised fixtures and quick-release clamps so adjustment happens off the machine.
- Streamline what remains. Parallel tasks, eliminated adjustments, marked settings, standard work for the changeover itself.
- Standardise and train, then measure every changeover against the new standard.
A worked example
A packing line changeover took 55 minutes. Recording it showed 20 minutes finding and fetching parts (external), 15 minutes of adjustment by trial (internal, convertible with marked settings), and 20 minutes of genuine internal work. After SMED: parts staged on a cart before the stop, settings marked, two people working in parallel on defined tasks. Changeover: 14 minutes.
Sustaining SMED
Changeover time is a measure for the tier board: each changeover against the standard, with reasons for any overrun. Drift shows within a week and becomes a problem to solve rather than a slow return to the old way.
Common mistakes
- Buying equipment before doing the first three steps.
- Treating SMED as a one-off event instead of a standard that is audited.
- Not involving the operators and setters who do the changeover.