What is lead time?

    Short answer

    Lead time is the total elapsed time from when a request is made until it is fulfilled, as the customer experiences it. In manufacturing it runs from order to delivery and includes waiting, queueing and transport as well as processing. It differs from cycle time, which measures only the time to complete one unit of work.

    Last updated · TeamAssurance

    The formula

    Lead time = date fulfilled − date requested. For a single process step: lead time = cycle time + waiting time. Because waiting usually dominates, two processes with identical cycle times can have very different lead times.

    Types of lead time

    • Customer lead time: order placed to order received by the customer.
    • Production (manufacturing) lead time: release to the floor until the finished product is complete.
    • Procurement lead time: purchase order to receipt from the supplier.
    • Cumulative lead time: the longest chain of procurement plus production needed to make the product from scratch.

    Lead time, cycle time and takt time

    Cycle time is how long one unit takes at a process. Takt time is the rate the customer requires. Lead time is the elapsed time through the whole chain. A value stream map shows the three together: processing time is typically a small fraction of lead time, and the gap is waiting, inventory and transport.

    How to reduce lead time

    1. Map the value stream and measure waiting at each step.
    2. Cut batch sizes so work does not queue behind the batch ahead.
    3. Reduce changeover time with SMED, which makes small batches practical.
    4. Balance the line so no step starves or floods the next.
    5. Remove approvals and handoffs that add waiting without adding value.
    6. Fix the causes of unplanned downtime and rework, which create queues.

    Why lead time matters on the board

    Lead time is the delivery measure the customer feels. On a tier board it sits beside schedule adherence and on-time delivery; when it slips, the daily meeting asks where work waited, and the answer becomes an action or a problem-solving project.

    How TeamAssurance helps

    In TeamAssurance, delivery measures such as lead time and schedule adherence appear on tier boards fed from ERP and MES data, slippage is discussed in the daily meeting with an owner and action, and lead-time reduction projects run as PDCA cycles linked to the measure.

    Frequently asked questions

    What is the difference between lead time and cycle time?

    Cycle time is the time to complete one unit at a process. Lead time is the elapsed time from request to fulfilment across the whole chain, including every wait.

    Is lead time the same as delivery time?

    Delivery time is usually the transport leg only. Customer lead time includes order processing, production and delivery.

    What is a good lead time?

    The one the customer is willing to wait, met consistently. Variation in lead time often hurts more than its average.