What is schedule adherence?

    Short answer

    Schedule adherence is a delivery measure of how closely an operation followed its production plan: the percentage of scheduled jobs or units completed in the planned period, sequence and quantity. It shows whether the plan is being executed, as distinct from throughput, which shows whether enough was made. Low adherence usually means problems were absorbed by reshuffling rather than solved.

    Last updated · TeamAssurance

    How to calculate schedule adherence

    Schedule adherence = scheduled items completed as planned ÷ scheduled items × 100

    Decide what "as planned" means and keep it stable: on the planned day or shift, in the planned sequence, and within a tolerance of the planned quantity. A common variant counts an order as adherent only if all three hold.

    Why it matters

    • The plan is where customer promises, material availability and capacity were reconciled. Every deviation unpicks that reconciliation somewhere else.
    • Reshuffling hides problems: a line that hits its volume by running whatever is available, rather than what was scheduled, looks productive while the real constraint goes unaddressed.
    • Low adherence creates expediting, extra changeovers, inventory in the wrong products and late deliveries.

    Schedule adherence on a tier board

    Show adherence per line per shift with the reasons for each missed item: material, equipment, people, quality, planning. The reason mix tells the Tier 2 meeting where to act. Planning problems (an unrealistic schedule) are as common a cause as execution problems.

    Improving schedule adherence

    1. Make the schedule visible at the line, by hour or by shift.
    2. Record every deviation with a reason at the time.
    3. Review the reasons daily; solve the recurring ones.
    4. Feed what the floor learns back to planning: lead times, changeover times and real capacity.
    5. Reduce changeover time so the schedule can be followed in small batches.

    Related measures

    On-time-in-full (OTIF) measures delivery to the customer; schedule adherence measures execution of the internal plan. Takt time sets the pace the plan should run to; OEE shows the equipment losses that break the plan.

    How TeamAssurance helps

    TeamAssurance tier boards track schedule adherence by line and shift with a reason logged for every missed item, so the Tier 1 and Tier 2 meetings see whether material, equipment, people or planning broke the plan. Recurring reasons move into structured problem solving, and the measure sits alongside OEE and quality on the same board.

    Frequently asked questions

    What is the difference between schedule adherence and on-time delivery?

    On-time delivery (or OTIF) measures whether the customer received the order when promised. Schedule adherence measures whether the internal production plan was executed as planned. An operation can hit delivery by expediting while adherence is poor, at a cost.

    What is a good schedule adherence target?

    Many operations aim for 95% or above, but the useful target is the one that drives the reasons for misses to be solved. A target met by making the schedule easier is not progress.