What is a RACI matrix?
A RACI matrix is a responsibility assignment matrix: a grid that names, for each task or decision, who is Responsible, Accountable, Consulted and Informed. "RACI matrix" and "RACI chart" mean the same thing. Its job is to stop work falling between functions, because every row must end up with one owner (A) and at least one doer (R). For the full definition and where the method comes from, see what is a RACI matrix; this page is the working template.
The blank template
| Task / decision | Role 1 | Role 2 | Role 3 | Role 4 | Role 5 |
|---|---|---|---|---|---|
| Task 1 | |||||
| Task 2 | |||||
| Task 3 | |||||
| Task 4 | |||||
| Task 5 | |||||
| Task 6 |
R = Responsible (does the work) · A = Accountable (owns the outcome; one per row) · C = Consulted (input before) · I = Informed (told after)
Sample RACI chart 1: closing a quality non-conformance
| Task | Operator | Supervisor | Quality manager | Maintenance planner | Site manager |
|---|---|---|---|---|---|
| Raise the non-conformance | R | I | A | ||
| Contain the affected product | R | A | C | I | |
| Root cause analysis | C | R | A | C | |
| Implement the corrective action | R | A | C | R | |
| Verify the fix held | R | A | I | ||
| Close and update the standard | I | R | A | I | I |
Sample RACI chart 2: a small improvement project
| Task | Project sponsor | Project lead | Process owner | Team member | Finance |
|---|---|---|---|---|---|
| Agree scope and goal | A | R | C | I | |
| Map the current process | I | A | R | R | |
| Choose and trial the change | C | A | R | R | C |
| Approve the spend | A | R | I | C | |
| Roll out and update the standard | I | A | R | R | |
| Review results after 30 days | A | R | C | C | I |
Notice that every row still has exactly one A. The sponsor holds it for the decisions only they can make, and the lead holds it for the delivery.
RACI example for an operations task: a machine breakdown
This RACI example covers an unplanned stop on a production line, from the moment the machine goes down to the update of the maintenance plan.
| Task | Operator | Supervisor | Maintenance technician | Maintenance planner | Production manager |
|---|---|---|---|---|---|
| Stop the machine and make it safe | R | A | I | ||
| Log the breakdown and call maintenance | R | A | I | I | |
| Diagnose and repair the fault | C | I | R | A | |
| Decide whether to reschedule production | R | C | C | A | |
| Test and hand the machine back | C | A | R | I | |
| Record the cause and update the maintenance plan | C | R | A | I |
Read the third row as a sentence: the technician repairs the fault (R), the planner answers for the repair being done properly (A), the operator is asked what they saw before the stop (C) and the supervisor is told when it is fixed (I). If you cannot read a row aloud like that, the row is not finished.
How do you build a RACI matrix?
- List the tasks or decisions, in the order they happen, down the left.
- List the roles across the top. Five to eight is usual; more than ten means the process should be split.
- Fill each cell. Blank is allowed and often right.
- Check each row: one A, at least one R, Cs only where their input genuinely changes the outcome.
- Check each column: a role that is A on every row is a bottleneck; a role with nothing but I may not need to be on the chart.
- Agree it with the people in the roles. A RACI nobody has seen is a wish.
What are the common mistakes?
- Naming people rather than roles.
- Making the senior person A for everything.
- Consulting everyone, so decisions wait for the slowest reply.
- Filing it after the kickoff and never looking again.
RACI and daily management
A RACI tells you who should own each type of action; the tier board shows whether they do. When an action type keeps being reassigned or overdue, the RACI is where the fix is made: give it a clear R and A and put it back on the board.
Step by step
- List the tasks. Every step and decision in the process, in order, one per row.
- List the roles. Across the top, as roles not names, five to eight of them.
- Assign R, A, C, I. Fill the cells; leave blanks where a role has no part.
- Check rows and columns. One A per row, at least one R, no bottleneck columns.
- Agree and publish. Walk it through with the people named, then put it where the work happens.
A worked example
A food plant kept missing CAPA closure dates. Their RACI for non-conformances showed the quality manager as A and R for every row, including implementing fixes on equipment the maintenance team controlled. Rewriting it made the supervisor R for implementation, the maintenance planner R for equipment changes and the quality manager A for verification and closure only. Overdue CAPAs fell within two months because each action on the board now had an owner who could actually do it.