What does PFMEA stand for?
PFMEA stands for process failure mode and effects analysis. PMFEA is a common mistyping of the same thing. It is one type of FMEA: a design FMEA (DFMEA) asks how the product design could fail, while a PFMEA assumes the design is right and asks how the process could make the part wrong. IATF 16949 requires it in automotive, and AS13004 covers it for aerospace.
What are the 7 steps of a PFMEA?
The AIAG-VDA FMEA Handbook (2019) sets seven steps:
- Plan and prepare. Agree the scope, the team and the timing.
- Structure analysis. Break the process into steps, using the process flow diagram.
- Function analysis. State what each step must achieve.
- Failure analysis. For each step, list the failure mode, its effect and its cause.
- Risk analysis. Rate severity (S), occurrence (O) and detection (D) from 1 to 10, then read off the action priority: high, medium or low.
- Optimisation. Assign actions with owners and dates to prevent the cause or detect it sooner, then re-rate.
- Document the results and share them.
What does a PFMEA example look like?
| Process step | Failure mode | Effect (S) | Cause (O) | Current control (D) | Action |
|---|---|---|---|---|---|
| Weld bracket | Weld too short | Bracket detaches in use (8) | Wire feed blocked (3) | Visual check each shift (7) | Weld monitor that stops the cell |
| Apply label | Wrong label | Customer receives mislabelled part (6) | Similar labels stored together (5) | Scan at packing (3) | Store labels by part number |
How does a PFMEA link to the control plan?
The documents form a chain: the process flow diagram lists the steps, the PFMEA finds the risks in each step, and the control plan records the checks and mistake-proofing that hold those risks down. Those checks then go into the operators' standard work and are verified by layered process audits.
When should a PFMEA be updated?
- Before a new process or product starts production.
- When the process, equipment, material or design changes.
- After a customer complaint, defect or near miss shows a failure mode that was missed or under-rated.
To start one, use the FMEA template, which has the worksheet columns and rating scales.